This will be a running log of activities as they occur for bringing back CDS after the planned outage over the weekend. Refer to Richard's alog about what happened over the weekend for prep.
We started the shift with lights, front gate operation, wifi, etc.
Step 6.3: LVEA Network Switches
This box appeared to be running (green lights & no errors).
Step 6.4 Work Station Computers
Work Stations powered in Control Room-----> But BEFORE these were powered up, The NFS File Server should have been checked in the MSR before powering anything up. This needs to be added to the procedure.
We have found several issues due to computers being started before the NFS File Server was addressed. These items had to be brough up again:
----->And the items above allow us to run Dataviewer now and also bring up the Vacuum Overview
Step 6.5 Wiki & alog & CDS Overview MEDM
They are back. Overview on the wall (thanks, Kissel).
Update: The wiki was actually NOT back since it was started before the NFS File Server was started. So the wiki was restarted.
Sec 8: EX (Richard & TJ)
They have run through the document & are moving on to other outbuildings. On the overview for EX, we see Beckhoff & SUSAUX are back.
Sec 10: MX (Richard & TJ)
Haven't heard from them, but we see that PEMMX is back on the Overview.
Sec 9: EY (Richard & TJ)
This is backonline. So now we can start front ends in the Corner Station!
They are now heading to MY now.....
Sec 11: MY (Richard & TJ)
...but it looks like MY is already back according to the CDS Overview.
STATUS at 10AM (after an hour of going through procedure):
Most of the CDS Overview is GREEN, -except- the LSC. Dave said there were issues with bring the LSC front end back up and will need to investigate in the CER.
End Stations: (TJ, Richard)
7.5 Front Ends (Updated from Kissel)
Everything is looking good on the CDS Overview
Sec 7.8: Guardian (updated from Kissel)
Working on bringing this back. Some of these nodes need data from LDAS (namely, ISC); so some of these may take a while.
BUT, basic nodes such as SUS & SEI may be ready fairly sooner.
7.1 CORNER STATION DC POWER SUPPLIES
These have all been powered ON (Richard).
(Still holding off on End Stations for VAC team to let us know it's ok.)
EY (Richard)
High Power voltage & ESD are back (this step is not in recovery document).
EX (Richard)
High Power voltage & ESD are back (this step is not in recovery document).
There appear to be some order issues here. (Jeff, Nutsinee, and others are working on fixing the order in the document.)
1) We held off on addressing DC high power because of wanting to wait for Vacuum System Team at the LVEA (for vacuum gauge) and at the End Stations (for vacuum gauge & the ESD).
2) We held off on some Corner Station items, because of them being on the Dolphin Network. So to address End Stations FIRST, Assigned Richard & TJ to head out to start the End Station sections of the document & get their Dolphin Network items online. Once they were done, Dave started on cornter station Front Ends on the Dolphin network.
Extraneous items:
Sec 7.6 LVEA HEPI Pump Station Controller
After Hugh's HEPI Maintenance, Jim brought this back.
Sec 8.5 EX HEPI Pump Station Controller
After Hugh's HEPI Maintenance, Jim brought this back.
Sec 9.5 EY HEPI Pump Station Controller
After Hugh's HEPI Maintenance, Jim brought this back.
UPDATE:
At this point (11:42am), we appear to be mostly restored with regard to the CDS side. Most of the operations subsystems are back (we are mostly green on the Ops Overview). The VAC group's Annulus Ion Pumps are back to using site power.
Lingering CDS/Operations items: