Reports until 13:19, Friday 04 May 2012
H1 PSL
oliver.puncken@LIGO.ORG - posted 13:19, Friday 04 May 2012 (2764)
Resassembly of the PSL (Part 3)
PSL installation team

May, 3rd 2012:

The IP adresses for the Beckhoff Computer had been changed. 
The channel names had been changed from H2 to H1. 
The Interlocks had been tested.

We started with the multimode alignment of the high power oscillator (see user manual for details on the alignment procedure).

The boxes with PSL components, stored in the mid station had been inspected. We did not open the boxes 3 and 4, since parts, which are stored in these boxes are supposed to be shipped to india. For all the other boxes we rearranged components, going either to india or to LLO as spare parts, which means that some of the sealed bags had been opened.
We stacked some of the boxes in order to get more space in the VEA.