H1 General
nutsinee.kijbunchoo@LIGO.ORG - posted 15:56, Wednesday 08 June 2016 (27653)
Ops Day Shift Summary

Morning Meeting

- ER9 in a month

- Extended maintenance is cutting in commissioning time. Try to not do it on Mon,Wed, Fri

SEI: No issue on recivering

CDS: "Fine"

Software: Don't assume things are perfect (due to the recovery from scratch).

FAC: Facility assessment tomorrow


Activities (All time in UTC)

~15:30 Fil to EX

16:00 Kristina to MX, Karen to MY

16:48: Robert setting up stuff by PSL

17:00 Robert out

18:04 Karen leaving MY

18:20 Betsy to LVEA

18:30 Betsy out

19:20 Fil back

~19:30 dave to Mid stations

20:00 Dave back

20:05 Betsy to optics lab

20:20 Fil to EX outside VEA (pulling cables)

21:01 Kyle to CP3 overfill

          Patrick, Krishna, Michael, Dave, Jim to EX to install BRS Beckhoff comp.

21:29 Kyle back

21:55 Dave+Jim back

22:07 Patric+Fil back

22:10 Fill dropping stuff at EX