Group Status:
-
SEI: Time in MICH, so can work on DRMI configs. Just monitoring BRS data.
-
SUS: -
-
Facilities: Wind Fence at EX construction begins
-
VAC: Encourage adjustment of Piranis (John).
-
PEM: Digging a hole at some time
-
PSL: DBB work tomorrow
-
CDS: Testing of common mode summing board (Ed)
Maintenance:
-
CDS: Binary for PRM rms (looking at cable) Filberto, EY PUM (pull chasis), Safety system stuff, CDS work stations reboot at 6am, resync atomic clock.
-
SEI: top level manager for guardian (TJ)
-
IOT2L Beam Dumps (beam and MC unlocked)
-
Guage on top of HAM1---so make sure we coordinate this with IOT2L work!!
-
Fire Dept testing bell in front room
Outreach:
respit from outreach visits. School group on Fri.