Reports until 08:09, Thursday 10 May 2012
LHO General
david.barker@LIGO.ORG - posted 08:09, Thursday 10 May 2012 (2809)
CDS wednesday summary, H1 and H2
H1: finished install of H1 PSL DBB TEST model. Later this was replaced by the actual DBB model and the ISS TEST model was activated. Work continues on the new PSL user account, specifically with regards to file sharing with the controls account. Start of DBB testing was delayed by the default-off behavior of the filter modules.

H2: New PEM models were installed on h2peml0 and h2pemey to conform to the new naming scheme.