Reports until 12:35, Friday 01 July 2016
LHO VE (CDS, VE)
patrick.thomas@LIGO.ORG - posted 12:35, Friday 01 July 2016 (28121)
Beckhoff vacuum controls upgrade Tuesday afternoon
On Tuesday afternoon, July 5, I plan to update the code on all of the Beckhoff vacuum controls computers (h0vaclx, h0vacly, h0vacmr, h0vacmx, h0vacmy, h0vacex, h0vacey). This is to use the new PID controller that has been installed and tested at end Y and mid X.

This will trip the ESD high voltage at end X and end Y. Also the cold cathode gauges will turn off and may take some time to refire.

This falls under WP 5972.