Engineering Run 9 (ER9) will begin next Wednesday. Here are some important details for operations:
-
ER9 begins Wednesday July 6, 2016 8:00am PT, 15:00 UTC, 1151 852 417 GPS
-
ER9 ends Friday July 8, 2016 23:59 PT, July 9, 2016 6:59 UTC, 1152 082 757 GPS
-
Target input laser power: 40W operation. (This may be adjusted to deal with PI modes and to optimize observing time.)
-
Only the H1 interferometer will be operational (a vent is on going at LLO)
-
"Simulated" data for L1 and Virgo
-
July 5th Maintenance: A maintenance day will precede ER9 next Tuesday. Please consider the interferometer and its controls under a code freeze until after ER9. Our focus is to have a stable, running H1 for ER9.
-
Plan for use of the calibration pipeline and DMT code running under SL7, with a fallback plan to run under SL6 if necessary.
-
ER9 Daily Telecon: Wednesday through Friday at noon PDT, 19:00 UTC, there will be ER9 Operational Status Telecons on the JRPC TeamSpeak channel.
Please see https://wiki.ligo.org/LSC/JRPComm/ER9 for more details.