Title: 07/12/2016, Day Shift 15:00 – 23:00 (08:00 – 16:00) All times in UTC (PT) State of H1: IFO unlocked. Maintenance day Commissioning: Outgoing Operator: None Activity Log: All Times in UTC (PT) 13:00 (06:00) Peter – Looking for missing equipment in laser enclosures. 13:15 (06:15) Peter – Transitioned LVEA to Laser safe 14:00 (07:00) Peter – Finished looking for equipment 15:00 (08:00) Start of shift 15:15 (08:15) Soda vendor on site for deliveries 15:36 (08:36) Ryan – Going into LVEA to recover computer equipment 15:55 (08:55) Joe – Going into LVEA to check eye wash stations 15:58 (08:58) Robert – Going into LVEA to work on PEM stuff 16:03 (09:03) Ryan – Out of the LVEA 16:04 (09:04) Paul – Going to End-Y to work on PEM stuff 16:09 (09:09) Narco - Deliver of N2 to CP2 (LX) 16:46 (09:46) Joe – Out of LVEA – Still has two forklifts on battery charger 16:50 (09:50) Cintas – On site to change out matts 16:55 (09:55) Kyle – RGA work at End-Y (WP #5992) 17:42 (10:41) Filiberto – Going into LVEA to check PSL and HAM6 racks 17:52 (10:52) Joe – Going into LVEA to check on battery charging 17:53 (10:53) Paul – Back from End-Y 18:06 (11:06) Joe – Back from LVEA – Battery chargers are off 18:24 (11:24) Paul – Going to End-Y to check PEM stuff 18:25 (11:25) Jeff K. – Running charge measurements on ETM-X 18:29 (11:29) Filiberto – Back from LVEA 18:31 (11:31) Filiberto – Going to Mid-Y 18:45 (11:45) Hugh – Going to End-Y to center STSs 19:06 (12:06) Filiberto – Leaving Mid-Y 19:08 (12:08) Hugh – Back from End-Y 19:10 (12:10) Kyle – Back from End-Y 19:11 (12:11) Jeff K. – Running charge measurements on ETM-Y 19:25 (12:25) Jeff K. – Finished with charge measurements at End-X 19:30 (12:30) Kiwamu – Transition LVEA to Laser Hazard 19:40 (12:40) Narco – Delivery of N2 to CP5 (Mid-X) 19:50 (12:50) Kiwamu & Nutsinee – Working on HWS Table (WP# 5990) 20:01 (13:01) Dick – Going into LVEA to check electronics racks 20:10 (13:10) Dick – Out of LVEA 20:55 (13:55) Twin Cities Metals on site to make delivery for Bubba 23:00 (16:00) Turn over to Ed End of Shift Summary: Title: 07/12/2016, Day Shift 15:00 – 23:00 (08:00 – 16:00) All times in UTC (PT) Support: Sheila, Jenne, Jeff K., Incoming Operator: Ed Shift Detail Summary: Maintenance day – All hands search of site for missing equipment. Equipment hunt has completed. Jeff K. ran charge measurements on ETM-X and ETM-Y. Did initial alignment and locked the IFO to DC_READOUT Commissioners requested high power – Lock broke just before reaching 40W. Relocking.