jeffrey.bartlett@LIGO.ORG - posted 00:02, Tuesday 19 July 2016 (28481)
Ops Evening Shift Summary
Title:  07/18/2016, Day Shift 23:00 – 07:00 (16:00 – 00:00) All times in UTC (PT)
State of H1: IFO locked at DC_READOUT_TRANS. 2.0W Wind is a light to moderate breeze. Microseism is low; seismic activity is slightly elevated in X, and Y but not out of line with wind conditions.   
Commissioning: Commissioners are commissioning. 
Outgoing Operator:  Ed 


End of Shift Summary:

Title: 07/18/2016, Day Shift 23:00 – 07:00 (16:00 – 00:00) All times in UTC (PT)
Support: Jenne, Sheila,        
Incoming Operator: N/A

Shift Detail Summary: Spent shift relocking in support of commissioning activities. Rode through a 5.5mag EQ in Chile with no apparent problems.