WHAM6 Vent Plan

Betsy Weaver, Keita Kawabe, Vern Sandberg

Jul 28, 2016

E1600229-v1,  WHAM6 Vent Plan

 

APPROVED work to be done in order of importance:

·      Assess HAM6 volume for contamination and investigation of possible beam corruption.  Take photographs.

·      Remove and inspect HAM6 OMC glass breadboard for damage, possibly swap with 3rd breadboard unit and realign

·      Install new High Quantum Efficiency PDs on OMC breadboard

·      Replace VE gauge on top of HAM6

 

DCC Vent Documents referenced in this plan:

·      M1600165 Mobile Cleanroom Relocation Procedure

·      T1600145 Cleanroom Move Checklist

·      E1100742 Payload layout update for HAM6

·      D0901822 HAM6 Top Level Chamber Assembly

·      E1201035 aLIGO Chamber Entry & Exit Procedures

·      M1100039 Hanford Checklist - HAM Door Removal

·      M1300464 Procedure for preparing aLIGO IFO for pumpdown

·      E1500214 OMC Black Glass Assembly Procedure

·      E1300201 OMC Assembly Procedure

·      D0900295 OMC SUS Assembly

·      D1201439 OMC Breadboard Layout

·      D1201515 OMC Transport Fixture

·      T1200525 How To Use the OMC Transport Fixture

·      T080117  Removal of OMC Breadboard

·      E1600013  Handling Procedure for High QE Photodiodes

 

Note – The in-chamber OMC team will consist of Koji, Corey, Jeff B, Betsy, Keita, while the VE and Seismic teams will be performing VE and Seismic line items.

SCHEDULE

FEW DAYS PRIOR TO VENT

1)    Move newly placed L4C’s that are on the LVEA floor, in the way of vent equipment

2)    Turn cleanrooms on around HAM6 where applicable

3)    First and second cleaning of HAM6 chamber area, door flange, and cleanrooms, etc.

4)    Stage supplies and equipment

5)    Contamination control kit

6)    3rd OMC Glass Breadboard unit

7)    2nd OMC transport fixture

8)    Clean spare ISC OM mirrors “just-in-case”

9)    ISC tool pan

10)SUS tool pan

11)Septum viewport cover D1200448

12)Confirm dust monitor is working

13)Lock HEPI

14)Confirm purge air capabilities of HAM6

15)Transition to LASER SAFE

 

TUE AUG 2, 2016

16)Confirm the PSL shutter is closed, then mark and move ISCT6 out of the way to facilitate door removal.  NOTE: DOCUMENT CABLING CONNECTIONS BETWEEN ISCT6 and HAM6.

17)Soft close GV5 and GV7 (backup safety)

18)Turn on purge air, if not done already

19)Vent HAM6

20)Remove NORTH and SOUTH CHAMBER DOORS – Review and follow M1100039 “ Hanford checklist – HAM Door Removal”

21)Entry chamber checklist items: Pick up floor CC wafers, inspect.  Take particle counter measurements and record. (Jeff B)  Notes:

 

22)Lock ISI (Team SEI)

23) Install Septum Window Cover

24) Inspect table components, specifically beam dumps, for damage

25) Start removal of necessary OMC black glass shroud pieces and stow on work table outside of chamber. (Betsy, Koji)

a.     E1500214 OMC Black Glass Assy Procedure

26)Remove ISI table masses that interfere with OMC work.

27) Install new High QE PDs on new OMC Breadboard Assy D1201439-03

a.     E1300201 Section 6.10 Replacement of photodiodes

b.     T1200525 Handling procedure for High QE PDs

28)Put First Contact on new OMC Assy D1201439-03 optical surfaces/PDs for cleaning.

 

WED AUG 3, 2016

 

29) Take daily particle measurements and record:

30)Continue removal of necessary OMC black glass shroud pieces and stow on work table outside of chamber.

a.     E1500214 OMC Black Glass Assy Procedure

31) Remove in-chamber OMC Breadboard Assy D1201439-02.  Place in transport fixture and stow on work table outside of chamber.   Although the removal process itself is not discussed in detail, it’s a reverse process of installation, so follow through the contents of the sections in the following order:

a.     T080117 Section 24 Suspending the masses

b.     T080117 Section 23.2 Attaching lower wires

c.     T080117 Section 21 Installing the metal bench

d.     T1200525 Using the OMC transport fixture

32) Inspect old OMC Breadboard D1201439-02.  If damaged, replace with Breadboard D1201439-03, following sections in this order:

a.     Remove First Contact from new OMC Assy D1201439-03 optical surfaces/PDs

b.     T080117 Section 31 Replacing the metal bench

c.     T080117 Section 21 Installing the metal bench

d.     T080117 Section 23.2 Attaching lower wires

e.     T080117 Section 24 Suspending the masses

 

THUR AUG 4, 2016

 

33) Take daily particle measurements and record:

34)Continue with OMC reinstall work.

35)Balance OMC suspension

a.     E1300201 OMC Assembly Procedure

36)Transition to LASER HAZARD

37)Align OMC with PSL beam

38)Align or confirm alignment of HAM6 optical paths

 

FRI ~TUE AUG 5~9, 2016

 

39) Take daily particle measurements and record:

40)Continue OMC and HAM6 optical alignment

41)Check Beam Diverter functionality

42)Check Tip Tilt TFs

43)Check for cable grounding

44) Rebalance ISI / transfer functions

45) Remove Septum Window Cover

46) Chamber closeout – perform applicable exit checklist tasks E1201035.

47) Take particle count measurements and record:

48)Replace HAM6 Doors

49)  Begin pump down

50)VE swap gauge on top of chamber

51)  Replace ISCT6 and reconnect all cables/light pipes.  Verify shutter functionality.

 