State of H1: Lightpipe is closed and locked, rotations stage is disabled at 2W, venting HAM6 tomorrow
Activities:
15:00-16:00UTC:
- morning meeting, alog 28769
- commissioning meeting
16:00-20:00UTC:
- JeffB - LVEA - dust count
- Fil/Alfredo/Elizabeth - HAM6/BSC3/BSC7 - pulling able to ITMX chamber for vacuum gauge
- tour in Control Room
- Hugh - helped with HAM6 SEI configuration, alogged here, alog 28773
- I took a snapshot of the last good alignment, alog 28779
20:00-22:00UTC:
- Chandra - MY - CP5 overfill
- Gerardo - EY - retrieved a yellow viewport cover
- Richard - disabled the rotation stage, alog 28786
- Richard - lightpipe locked, alog 28788
- Kyle - LVEA - measured dewpoint, alog 28782
- JimW/Micheal/Krishna: JimW + UW crew
- bringing in a new seismometer
- will be careful to avoid adding contamination to the LVEA
- will be taking it to the vertex - hand cary over or slide under the beamtube
- Fil/Alfredo/Elizabeth - HAM4, BSC3, BSC7 - pull new cable to vacuum gauge on BSC7
- Peter/Jason - PSL air conditioning has been changed, no entry into the PSL as of 22:00UTC
- Nutsinee - LVEA - TCS
- HAM6 ISCT6 moving crew - LVEA - moved the table away from HAM6 - Jenne, Keita, TJ, JeffB
- Gerardo - LVEA - HAM6 - covered a viewport with a yellow cover
- JeffB - LVEA * 4 - checking air quality / dust - other vent prep
- Robert/Richard/Fil - on the roof for anemometers
- Robert/Fil/Richard - back from the roof
- Jenne, TJ, Keita - out of the LVEA
- Chandra - back from MY
- Gerardo - back from EY
- Richard - back from LVEA
- Nutsinee - back from the LVEA
- Gerardo - back from HAM6
- JeffB - out of the LVEA
22:00-22:35UTC:
- JimW - out of the LVEA
- Fil/Alfredo/Elizabeth - out of the LVEA
22:35-23:00UTC
- Krishna/Micheal - out of the LVEA
23:00UTC - end of OPS coverage today - no eve shift OPS this week due to HAM6 vent
Tomorrow - known activities:
- vent HAM6 and remove door(s)
- craning - Bubba
- seismometer setup - Micheal/Krishna
- Peter and Jason - out of the PSL