chandra.romel@LIGO.ORG - posted 14:15, Tuesday 02 August 2016 (28811)
HAM 6 vent
Bubba, Chandra, Gerardo, Kyle

HAM 6 took one hour to vent to atmosphere, The north & south doors were removed before lunch. GV 5 & 7 were soft closed prior to vent. Attached is vent pressure plot from today and also from April, for comparison.

NOTE: in addition to powering off all HV in HAM 6, we also powered down the ITM HV.