Displaying report 1-1 of 1.
Reports until 09:00, Friday 19 August 2016
H1 General
edmond.merilh@LIGO.ORG - posted 09:00, Friday 19 August 2016 (29193)
Morning Meeting Summary

SEI - progress made to miigate tripping of HAM6 ISI when fast shutter is activated

SUS -  no report

CDS - hopeful to close out gust meter work today; PEM AA chassis repaired; TCS AA chassis repaired. Both AA chassis suffered buffer chip damage most likely due to 'hot-swapping'.

CDS SW - continuing worl to address Frame Writer instability issues. Also, formulate a plan for '02

PSL - water leak is repaired. Optics have been wiped. Further inspection of collateral water issues will be performed. Power up of LASER hopeful for this afternoon. TCSY is back up and fully functional at full power. No hard evidence of BS OpLev glitching noted. If said glitchiness persists there will be a plan to swap out the laser.

VAC - will transition HAM6 to ION pump. RGA bakeout work between HAMs 4 and 5 will continue into tomorrow. Length of time most likely will depend on commissioners being able to return to their tasks.

FAC - Bubba will inish eyewash station inspections. DI skid will be re-plumbed'