Reports until 13:55, Tuesday 23 August 2016
H1 CDS (DAQ)
david.barker@LIGO.ORG - posted 13:55, Tuesday 23 August 2016 - last comment - 14:06, Tuesday 23 August 2016(29251)
DAQ restart, latest corner station Beckhoff slow controls code

After Daniel's h1ecac1plc1 code changes, I have installed the new INI file and restarted the DAQ.

Comments related to this report
daniel.sigg@LIGO.ORG - 14:06, Tuesday 23 August 2016 (29252)

This TwinCAT update included:

  1. A better lock loss monitor by triggering on the transmitted arm power,
  2. Adding save/restore functionality to the PEM library,
  3. Fixing the save/restore for the RF chanels in the corner PLC2,
  4. Marking 2 ouptut channels as readonly in the laser power controller.