Reports until 00:00, Tuesday 30 August 2016
LHO General
thomas.shaffer@LIGO.ORG - posted 00:00, Tuesday 30 August 2016 (29378)
Ops Eve Shift Summary

TITLE: 08/30 Eve Shift: 23:00-07:00 UTC (16:00-00:00 PST), all times posted in UTC
STATE of H1: Commissioning
INCOMING OPERATOR: None
SHIFT SUMMARY: Commissioning work continues. The violin modes were rung up a bit from a large eathquake yesterday and Jeff K worked to damp them out. Sheila and I ran into some TCS rotation stage issues that we "fixed" by logging into the system manager and temporarily changing the warning flag values. Meanwhile the TCSX was putting 2W into the IFO so ITMX is a bit hot and still cooling down.