Work Permit Summary for 2016 August 30

Work Permit Date Description alog
6130.html 2016-08-30 10:58 Activity: Crane the following: scissor lift next to BSC4 (northwest corner) and turbo pump cart. Install new hot ion gauge assembly on existing valve near top of BSC4. Need to pump down small air volume using a pump cart.
Area of Activity: VE, BSC4, install hot ion gauge
29387
6129.html 2016-08-29 15:37 Activity: Replace, repair, and/or reconfigure semi-permanent cleanroom curtains in LVEA and both end stations.  
6128.html 2016-08-29 13:45 Activity: Move the clean room that is currently located on south side of output arm a few feet away from the tube to allow for curtain repair and then return the clean room to the original location.  
6127.html 2016-08-29 12:50 Activity: Install and configure a new DMT to EPICS bridge so that we will continue to reflect the DMT signals (range) into EPICS in near realtime after the AUTH/LIAM project updates the authentication server infrastructure.  
6126.html 2016-08-29 11:43 Activity: Activity: Connect output of Inficon guage (HAM6) to a safety interlock in the CER Mezzanine. Interlock enables/disables the high voltage power supplies to the Fast Shutter and PZTs. This will involve shutting down the associated HV supplies. Will coordinate with vacuum team when connecting/disconnecting to vacuum gauge. A safety interface relay chassis D1400047 will be installed on top of rack in CER.  
6125.html 2016-08-29 11:40 Activity: Reconfigure h1fw1 to match h1fw0. * new executable (daqd build on h1fw0) * new configuration Configure h1fw2 to run the old build (currently on h1fw1) for now.  
6124.html 2016-08-29 10:52 Activity: Re-epoxy 2 seismometers to the floor near where the HAM6 doors are stored during a vent. They were removed during the HAM6 vent, and need to be re-installed.
Area of Activity: NN array, LVEA floor
29385
6123.html 2016-08-29 08:50 Activity: ETMy oplev maintenance. Power cycle ETMy oplev AA chassis. This is to hopefully solve the issue where the oplev is reporting the optic moving by > +-0.5 urad while locked, which shouldn't be possible. Tweak ETMy oplev laser power to address laser glitching. No view ports will be exposed during this work.
Area of Activity: ETMy Optical Lever
29386
6122.html 2016-08-26 10:26 Activity: Fix some errors in h1psliss model and restart. Some testpoint names are changed so this needs a DAQ restart.  
6121.html 2016-08-25 16:16 Activity:

Turn on remote access controls during business hours. This will limit remote ssh access to CDS to users who have approved work permits and have been granted access by the operator.

The purpose of this to test the remote access control system, by allowing operators to administer the system and to condition the remote users to acquiring a work permit and coordinating with the operator prior to remotely accessing CDS.

At this time it is proposed that this system only be enabled 8am - 4pm Monday-Friday while there is typically operator coverage. During O2 this could be enabled 24x7.

As users will be locked out of CDS until coordinating with the operator, it is expected that there will be increased support requests until users and operators get used to the workflow.

Documents: T1500529
 
6120.html 2016-08-24 13:56 Activity: Add dolphin network card to PSL Add 3rd loop ISS Model changes to ISS and LSC  
Older Permits      
6089 22:36, 30 August 2016 Annulus Ion Pump Cables Pulled and Landed 29405
6119 09:30, 30 August 2016 GC core router will be removed and replaced 29382
5986 09:56, 30 August 2016 HEPI Pump Station #1 back in service 29384