LHO General
patrick.thomas@LIGO.ORG - posted 00:05, Wednesday 07 September 2016 (29508)
Ops Evening Summary
Jenne, Stefan, Terra, Jamie and Sheila commissioning.

Peter and Jason finished work on the PSL at the beginning of the shift. Stefan started and I finished an initial alignment. Jenne and I had to change the fiber polarization in the MSR. We encountered issues with engaging the DRMI ASC loops again. This was mostly dealt with by stopping at LOCK_DRMI_1F and moving the optics to minimize the ASC error signals before engaging the control loops. The striptools for these are in /opt/rtcds/userapps/release/isc/h1/scripts. They are PITCH_ASC_ERROR_SIGNALS.stp and YAW_ASC_ERROR_SIGNALS.stp. There was a 300nm dust alarm in the PSL102 room. I trended the channel back and it appears to have happened a number of times before. I changed the ISI configuration from 'very windy' to 'windy'.

23:12 UTC Jenne to LVEA to measure noise of seismometer
23:18 UTC Jenne back

Jason and Peter done in PSL, Stefan starting initial alignment

23:52 UTC Jenne and I changed polarization in MSR
00:11 UTC Initial alignment done
01:55 UTC PSL102 300NM dust alarm warning
03:16 UTC Changed ISI configuration from 'very windy' to 'windy'