Reports until 14:57, Thursday 31 May 2012
H1 FMP
jodi.fauver@LIGO.ORG - posted 14:57, Thursday 31 May 2012 (2997)
BSC2-HAM4 ICC
In HAM4, the hand-brushing around the fins and first vacuum were completed this morning. This afternoon, wipe down and second vacuum were completed. Inspection should be completed by the end of the day.

Flooring for BSC2 was brought from the VPW to the LEA. It will be installed after the dust barrier is removed from between BSC2 and HAM4. That activity should take place early tomorrow and then the door can be returned to HAM4.