On Friday, after spending some time with Hugh, Bubba and I made a brief checklist (See below) to coordinate our efforts in the BSC1-HAM2 area.
1. Friday pm
-Second cleaning BSC1
2. Friday pm
-Move A-frames and I-beams to HAM 2 area
3. Monday am
-Move cleanroom from HAM4 to HAM5
-Remove doors and dome from BSC1
-Stage Optics extract equipment at BSC1 South
-Install SEI Soft Roof and adjust cleanroom location at HAM2
4. Tuesday am
-Move Garbing/Staging cleanroom from HAM2 to BSC1 South
-Optics de-install BSC1 (Lead: Cheryl, Apollo help)
-Move Garbing/Staging cleanroom from BSC1 to HAM2
5. Tuesday pm
-BSC1 ISI de-install (Contact Dale)
6. Wednesday am
-Set up A-frames, etc at HAM2
7. Wednesday pm
-Install HAM2 ISI