Reports until 08:04, Monday 04 June 2012
H1 INS
jodi.fauver@LIGO.ORG - posted 08:04, Monday 04 June 2012 (3023)
BSC1 ICC-HAM2 ISI Install Prep
On Friday, after spending some time with Hugh, Bubba and I made a brief checklist (See below) to coordinate our efforts in the BSC1-HAM2 area.

1. Friday pm
     -Second cleaning BSC1
2. Friday pm
     -Move A-frames and I-beams to HAM 2 area
3. Monday am
     -Move cleanroom from HAM4 to HAM5
     -Remove doors and dome from BSC1
     -Stage Optics extract equipment at BSC1 South
     -Install SEI Soft Roof and adjust cleanroom location at HAM2
4. Tuesday am
     -Move Garbing/Staging cleanroom from HAM2 to BSC1 South
     -Optics de-install BSC1 (Lead: Cheryl, Apollo help)
     -Move Garbing/Staging cleanroom from BSC1 to HAM2
5. Tuesday pm
     -BSC1 ISI de-install (Contact Dale)
6. Wednesday am
     -Set up A-frames, etc at HAM2 
7. Wednesday pm
     -Install HAM2 ISI