Reports until 09:50, Friday 07 October 2016
H1 General
jeffrey.bartlett@LIGO.ORG - posted 09:50, Friday 07 October 2016 (30301)
08:30 Meeting Minutes
SEI: All OK – Working on ESs sensor correction
SUS: No Report
CDS Ele: All OK
CDS Swt: All OK – Fixed problem with bad commissioning frame effecting NDS
PSL: All OK – PSL has been running since the Diode controller swap
TCS: No Report
VAC: All OK – Kyle planning for the 5 day RGA bake out at End-X