Reports until 18:00, Tuesday 05 June 2012
LHO General
jonathan.berliner@LIGO.ORG - posted 18:00, Tuesday 05 June 2012 (3039)
Tuesday Ops Log
- BSC1: moving garbing room, setting up lazy susan. Cheryl de-installed ITMY, preparing it to be sent to KAGRA. ICC will commence from north side of biergarten.
- BSC6: Long pump-down begins today, with Gerardo leading.
- Praxair delivery for CP6 and CP8.
- Electrical contractor working on DC power supplies at EY.
- FMY electronics still misbehaving...Richard addressing.
- Apollo grouting at H2 input, HAM7, MC legs.
- PSL working on controls, DAQ.
- Platt Electric makes delivery for Richard.
- One Apollo delivery in the afternoon.
- Transit of Venus broadcast in Control Room. Some visitors on site expected for LHO's special event. Unfortunately, the sky was overcast for the entire day, so the sun was not visible at LHO as of 18:00. Check back here on 8 Dec 2125, LHO's next chance.
- OSB doors locked at 16:45.