H1 General
vernon.sandberg@LIGO.ORG - posted 10:50, Wednesday 19 October 2016 (30657)
Work Permit Summary for 2016 October 18

 

Work Permit Date Description alog/status
       
6258.html 2016-10-18 10:10 Reconfigure DAQ to rename the old commissioning frame as the new full/raw frame. Stop writing the smaller old science frames. Reconfigure NDS to serve these renamed frames. Co-ordinate with LDAS on archival. 30623, 30637
6257.html 2016-10-18 08:52 Perform scheduled maintenance to scroll compressor #3, #4, #5 @ Y-End vent/purge-air supply skid. Maintenance activity will require for the compressors to run for brief periods of time. Lock-out/tag-out power to skid. 30631
6256.html 2016-10-18 08:28 Update software on timing RF Counter/Comparator with release 5 which disables 4 internal LED's. 30625
6255.html 2016-10-17 15:59 Activity: (see also WP #6221) Start and run rotating pumps while baking RGA using variac-limited flexible heaters.  30630
6254.html 2016-10-17 15:36 Pick empty BSC ISI storage container with load cell attached to obtain accurate weight of the container. (This work is in support of 3rd IFO efforts.)  30632
6253.html 2016-10-17 14:17 Place HWS cameras (LVEA & EX) on temporary power supplies, same configuration as EY. Will need laser hazard at EX and LVEA. ECR 1500251 FRS 4559  30644
6252.html 2016-10-17 13:54 Update the DMT calibration code to gstllal-calibration 1.0.6. This release contains a few bug fixes based on testing from this week's lock stretches for the coherence gating for the kappa calculations. 30626
6251.html 2016-10-17 12:07 Upgrade all front end models and all DAQ systems to RCG 3.2 Will require restarts of all models and of the DAQ. During the upgrade no front end data will be recorded (EDCU will be ran to trend VAC). Est. front end down time about 1 hour. 30609, 30637
6250.html 2016-10-17 11:19 Investigate glitches revealed by Omicron. Complete routine maintenance- diagnosing and tuning OFS, etc. May include blocking Pcal beam for extended periods to diagnose source of glitches. 30548
6249.html 2016-10-17 09:05 Install two thermocouples inside cyropump #3 exhaust pipe and connect to existing CDS PV signals: HO:VAC-MY_CP3_TE202A_DISCHARGE_TEMP_DEGC & HO:VAC-MY_CP3_TE202B_DISCHARGE_TEMP_DEGC. This will require removing the exhaust check valve.

https://alog.ligo-wa.caltech.edu/aLOG/index.php?callRep=30662

6248.html 2016-10-17 08:57 Investigate and repair broken readback on some RF amps, AMP18M, AMP24M1, and DIV40M.  30633
6247.html 2016-10-17 08:57 Pull power and network cable for RGA in corner station. Work will consist of climbing over HAM4 and pulling around BSC2 and BSC3.  30635
6246.html 2016-10-17 08:55 Investigate and repair H1:ISC-RF_C_DIV40M_POWEROK 40Mhz divider readback.  30633
6245.html 2016-10-13 13:51 Turn off cdswiki to clone its hard drive and move the server to a newer hardware due to system failures  
Previous Work Permits      
6237.html 2016-10-10 15:43 Remove the Solaris QFS/NFS server h1ldasgw2. This was installed in the summer to NFS export frames to the NDS servers. It has served corrupted frames, so we will return to the previous configuration. 30637