Reports until 16:49, Tuesday 25 October 2016
H1 CDS (TCS, VE)
filiberto.clara@LIGO.ORG - posted 16:49, Tuesday 25 October 2016 (30799)
CDS - Tuesday Maintaince

FRS 4559
WP 6247

EX:

1. Placed HWS camera on seperate power supply. The power supply is underneath the ISCTEX table.
2. Finished cabling for RGA at EX.

LVEA:

1. Placed HWS cameras (X & Y) on seperate power supplies.
2. Terminated network cable for RGA in LVEA. Network cable is pulled to SUS-R3. Connection to switch needs to be made in CER.
2. Placed power distribution boxes (24V regulated down to 12V)  for the ITM spool cameras, for both X and Y arms.
2. Placed junction box and landed power cables on top of H1:SUS-R5. This is part of the ongoing work for the 24V digital power distribution.
3. Started work on junction box on top of H1:SUS-R6.

The software for the HWS cameras needs to be restarted.

F. Clara, E. Merilh