Displaying report 1-1 of 1.
Reports until 16:00, Wednesday 26 October 2016
H1 General
travis.sadecki@LIGO.ORG - posted 16:00, Wednesday 26 October 2016 (30900)
Ops Day Shift Summary

TITLE: 10/26 Day Shift: 15:00-23:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Lock Aquisition
INCOMING OPERATOR: TJ
SHIFT SUMMARY:  First half of the shift was dedicated to Kiwamu/Jason chasing PSL alignment.  As soon as they determined that the pointing was OK, and gave me the go-ahead to start locking, we were hit by the 6.1 EQ in Italy.  After waiting for that to ring down, Jenne and I began diagnosing the issues with INPUT_ALIGN during Initial Alignment.
LOG:

16:07 Chandra, John to MY

16:50 Richard to EY

17:00 Jason, Kiwamu to PSL

17:37 Richard back

17:38 Betsy to LVEA

18:10 Jason, Kiwamu out

18:12 Betsy out

18:59 Jason, Kiwamu to IOT2L

19:02 Chandra back, going to EX

19:49 Betsy to LVEA TCSy table

19:55 Kiwamu to LVEA marking wall

22:08 Chandra to MY
 

Displaying report 1-1 of 1.