H1 FMP
jodi.fauver@LIGO.ORG - posted 13:16, Wednesday 13 June 2012 (3114)
BSC1 ICC
The FTIR paperwork was generated and the kit shipped off to JPL.  The dome was returned to the chamber and the permanent flooring was installed. With a crew working on either side of the chamber, the doors were returned after being vacuumed and wiped. All ICC activity was completed by lunch. The cleanrooms will be moved after lunch.