- Terry and Christina finished cleaning HAM5 and HAM6. - Apollo installing cable trays at HAM1 output. - Electrical work for HVAC in LSB fiber bonding lab. - Thomas aligning OpLevs. - BSC1 ICC ongoing. - Gerardo leak-checking BSC6's volume. - HAM ISI prep into HAM3. - Fine actuator install at HAM1. - Jim working on HAM2, cabling. - Richard installing cable trays on output arm. - Lacing tray installation for SUS cabling. - 09:50 - Bob from Mid-Columbia Forklift arrives. - Craning of cleanroom, actuator install. - Vincent recompiled filters. - 13:00 - Oxarc arrives - Safety meeting at 3pm - OSB Doors locked at 4:15pm