TITLE: 11/05 Eve Shift: 23:00-07:00 UTC (16:00-00:00 PST), all times posted in UTC
STATE of H1: Aligning
INCOMING OPERATOR: TJ
SHIFT SUMMARY: IFO has been up and down all night for various reasons. After 2 of the 4 locklosses, ITMy swung around for a long time, slowing relocking. Stefan looked for the cause but was unable to find one. Also, the ASAIR and POPAIR signals have been oscillating during full lock. Matt and Stefan are looking into the cause of this, but as of the end of my shift have not come to a conclusion. I ran A2L for 2.5 of the locks, the 0.5 being that I was halfway through the 2nd script when we lost lock. Stefan said that it was useless to run A2L with the AS and POP oscillations, so I haven't run it for the last lock. Microseism is still above the 90%ile level. Wind is calm. Locked at ~70MPc.
LOG:
23:59 Updated LSC and ASC SDF OBSERVE.snap files per Hugh's request. If the Owl shift operator has a lockloss, he'd like to update the LSC and ASC DOWN.snaps as well.