Discussion of weekend's activities & then going through the subsystems.
-
SEI: HEPI flushing stand in Mechanical Room (Hugh & Jim)
-
SUS: Nothing
-
CDS: High Volt supply trip over weekend at EX. Replacement is coming to be tested & replaced. (Mention you should probably turn off other power supply when this happen...specifics in Ops Wiki/alog/Power Outage Document (Richard M)
-
Software: Nothing
-
PSL: Nothing
-
Vacuum: Nothing
-
Facilities: Leak Hunting (Bubba)
-
Commissioners: Nothing
Work Permit Review.
Tues Maintenance Outlook:
-
ADC Card install in PEM Chasis (Jim B)----> Plan to do this "Computer Activity" first thing in the morning & then allow other work to continue after!
-
PCal Calib EX & EY (Savage)
-
HEPI Pringle Guardian removal attempt (Hugh)
-
Realign Oplevs (PR3 SR3 & Quads) (Ed)
-
PSL Alignment checks (Jason)
-
EX Turbo spin up in VEA (Kyle)
-
DC power work in Beer Garden. Shut off PDs for beam baffle among other auxilary things (Richard & Crew)
-
Shoot For Maintenance Ending At Noon!