Ops Day Shift Summary

TITLE: 11/28 Day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Corrective Maintenance
INCOMING OPERATOR: Jim
SHIFT SUMMARY:  After the lockloss, we have been in DOWN for PSL PZT work, with other tasks happening opportunistically.
LOG:

16:12 Joe D beamtube patching Yarm

17:37 Lockloss, possibly due to coincident PSL Noise Eater OOR

17:58 Kyle to LVEA PT180

18:06 Jason to EX for OpLev work

18:10 Robert and Kiwamu to PSL PZT work

18:15 Joe D done

18:20 Kyle out

18:22 Jeff B forklifing chiller

18:25 Hugh to EX BRS work

18:30 Jason done at EX

18:33 Jason and Betsy to TCSy table to check flow sensor

18:54 Jason to EY OpLev, SEI_CONF to SC_OFF_NOBRSXY

19:08 Jeff B done

19:21 Jason done

20:02 Hugh done, SEI_CONF set to WINDY_NO_BRSX (Hugh said not to use BRSX yet)

22:08 Switched SEI_CONF back to WINDY since Hugh reports that BRSX is back up

22:34 Dave restarting models

23:55 Kyle to LVEA to close valve