Reports until 19:45, Thursday 21 June 2012
LHO General
jonathan.berliner@LIGO.ORG - posted 19:45, Thursday 21 June 2012 - last comment - 10:25, Friday 22 June 2012(3215)
Thursday Ops Log (One Arm Test Edition)
- One Arm Test Begins: Gate valves opened, and the laser has been sent down the arm. If you find the beam, let Keita or Rana know ASAP.
- Safety discussion: If the work involves manipulating components in the beam path, including viewport covers and gate valves, the LSO must be notified. In addition, all viewport covers must bare a warning that removal requires approval by the LSO.
- BSC8: Transfer functions today. Discussions at morning meeting about coordinating cleaning with measurements. Decision was to hold off on cleaning until this is resolved. Also, GV-6 was opened. In addition to Illuminator lights, Rana and Keita were using a flashlight to locate the green laser beam.
- BSC6: HEPI transfer functions. Richard installed cameras yesterday and set up the Illuminator lights. The cameras are still being worked on, as the analog feed from EndY is not great.GV-17 was opened.
- HAM5: ICC ongoing.
- HAM2: ISI - Electronics work.
- HAM3: ISI - Richard doing cable-pulling prior to entry
- ISCT4 is cleaned and ready to be moved to Betsy's spot.
- H1 PSL: Michael worked on the software and network connections.
- MidX everything out, grout beginning next week.
- EndX prep beginning.
- Craning: Moving doors in the LVEA (HAM5 and HAM6), crane in staging building (Corey).
- LSB HVAC work to begin Friday morning.
- Pickup+Delivery of cardboard recycling.
- Riverside High School visited in the morning.
Comments related to this report
corey.gray@LIGO.ORG - 10:25, Friday 22 June 2012 (3227)

Excellent Summary for your final Operator log.  :) We'll miss 'em!