Displaying report 1-1 of 1.
Reports until 18:00, Wednesday 10 November 2010
LHO FMCS
kyle.ryan@LIGO.ORG - posted 18:00, Wednesday 10 November 2010 (324)
X-end & Y-mid
X-end - Previous attempt at drying X-end volume (see entry from 11/9/2010) was too laborsome for minimal benefit -> Tried different approach today.  Roughed down volume to <100 torr then backfilled to ~1 psig with dry air this resulted in -35C air blowing out of VE when purge line decoupled -> Repeated exercise this time going down to <10 torr then backfilling -> will pump X-end normally tomorrow. 

Y-mid - Shutdown Y-mid turbo and QDP80
Displaying report 1-1 of 1.