16:29 Fil , J. Batch ad John Worden out to LDAS.
16:42 Jim. Johm and Fil back from LDAS. Electrical panels are tripped. Electrician is on his way to investigate. Still not sure what order things went down.
16:46 Lockloss EQ
16:50 Switched ISI config for Large EQ in Northern California.
17:04 Switch ISI config back to Windy after quick decay of EQ
17:20 GRB alert. H1 not locked
17:34 H1 locked and observing. Monitoring f1 violin modes which are slightly rung up.
19:14 Fil reports that the LDAS power panel trips were due to the room, first, overheating. Queries into remote monitoring of LDAS room temps are being made.
19:17 filed FRS ticket for noisy ops station computer fan.
20:12 lockloss HAM5 and 6 ISI tripped
20:20 HAM5 CPS glitching. Jim out to power cycle chassis in CER.
20:34 Jim and Fil out to LVEA to physically "exercise" CPS connections.
21:30 Recieved Hanford Release advisory. Decided that I should get my non-snow ready vehicle home. TJ is there as well as Patrick who is the evening shift operator.
Assuming Ed meant to mark this entry for 12/14.
Assuming Ed meant to mark this entry for 12/14.