Reports until 16:08, Tuesday 26 June 2012
X1 SEI
corey.gray@LIGO.ORG - posted 16:08, Tuesday 26 June 2012 (3268)
HAMISI#7 Optics Table Installation

(corey, greg, jim)

The granite table is now clear of the HAMISI#7 Optics Table.  This table was installed with minimal fanfare and no issues.  It has been torqued down. 

(The springs were pulled down, Flexures installed, the Springs are now pulling up on the Flexures, Pull-Down hardware is still in places [it will be removed once we have the Optics Table torqued down])