(corey, jim)
Dial Indicator Install (this work was on Tues)
Dial Indicators used to monitor the HAM3 ISI/HEPI system are roughly in place. This hardware should not be touched/bumped as it will be used to monitor and ultimately help position the HAM3 ISI.
Cabling (this work started Wed)
In-Vac Cabling for HAM3ISI is mapped out according to D1002874. Since Septum work finished up this afternoon, I started running Corner-1 cables to their feed through. I was able to get all cables to the feedthrough (but opting NOT to screw down to feed-thru), EXCEPT for the H1 Actuator (it's 70" long cable was a foot or so too short!). At any rate, I only ran cables for Corner-1. I went to the other side of the chamber and separated Corner-3 cables from Corner-2 (since they're going to opposite sides of the Chamber). Corner-3 looks like it will be the tough one to work on (due to feed-thru in middle of Chamber).
I labeled the dirty side of feedthroughs.
H1 Actuator cable will be replaced with a 135" (shortest available now)