Reports until 07:16, Wednesday 27 June 2012
H1 INS
jodi.fauver@LIGO.ORG - posted 07:16, Wednesday 27 June 2012 - last comment - 08:20, Wednesday 27 June 2012(3273)
Prep for HAM6 bellows install
John, Hugh, Bubba and I agreed on path toward installation of the SEI support tubes, bellows and table. Please see list below. 

1. Remove septum at HAM3/Inspect for identified leak/-Apollo-Cleanroom in place/Kyle worked on this yesterday
2. Test septum at HAM5/6-Kyle-Cleanroom in place
3. Move ion pump from HAM5 to HAM6-Kyle-Cleanroom in place/Kyle worked on this yesterday
4. Install all possible feedthroughs on BSC1/2/3 and HAM4/5/6; blank off as needed-Apollo-Appropriate purge needed/Hugh is working on this	
5. Install support tubes, support table and bellows per E980268 at HAM6-SEI/Apollo-Cleanroom in place
6. Pump down and leak check volume-Kyle/Gerardo/John-No cleanroom needed
Comments related to this report
john.worden@LIGO.ORG - 08:20, Wednesday 27 June 2012 (3275)

We plan to leak check between step 4 and 5 in order to avoid any ambiguity when testing the support tube bellows. So there will be two pump down/leak test cycles.

If leaks are found there may be additional pump/test cycles.