Maintenance Discussion: Aiming for short day, but if we have long tasks, it could be allowable.
-
TCSy Flow Sensor (Jason)
-
PSL Injection, requires H1 (Robert)
-
Magnetometer L2 Coil Driver or replace the Driver (Robert, Fil)---> Will address today
-
Upgrade software on rate controller for file server, first thing in the morning (8-8:30, Carlos)
-
iMac replacements in Control Room (Carlos)
-
2k IMC tube run pump carts for 4hrs(kyle)
-
RefCav touchup (Peter)
-
Dust Monitor test (Jeff)
-
Curtains in LVEA (Jeff)
-
Access System work (Fil)
-
ITMX oplev (jason)
-
Contractor cutting ashphalt at vpw (bubba)
Went over Work Permits.