jodi.fauver@LIGO.ORG - posted 10:47, Friday 29 June 2012 (3307)
Xend Prep
Below is the checklist we are using to guide work at Xend. So far, we've only agreed on sequence of events through all grouting.

1. Retrofit chamber cleanroom-done
2. Position BSC9-done
3. Set BSC9-should be done today
4. Position/set BSC 9 HEPI piers
5. Build 1 Type C cleanroom
6. Cleanings
7. Stage for spool install
8. Install/set spool pieces and legs
9. Grout BSC9, HEPI piers, spool legs