Below is the checklist we are using to guide work at Xend. So far, we've only agreed on sequence of events through all grouting. 1. Retrofit chamber cleanroom-done 2. Position BSC9-done 3. Set BSC9-should be done today 4. Position/set BSC 9 HEPI piers 5. Build 1 Type C cleanroom 6. Cleanings 7. Stage for spool install 8. Install/set spool pieces and legs 9. Grout BSC9, HEPI piers, spool legs