H1 General
edmond.merilh@LIGO.ORG - posted 15:59, Tuesday 24 January 2017 (33599)
Shift Summary - Day
TITLE: 01/24 Day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Observing at 65Mpc
INCOMING OPERATOR: Nutsinee
SHIFT SUMMARY:
Maintenacne day went well. It went about 1.5 hours over midday. Re locking was not a problem except for a small guardian script glitch that kept us from advancing beyond DRMI_LOCKED, briefly.
LOG:
	16:05 UTC Dick G. starting WP 6453
16:10 UTC Bubba to endY to start fan lubrication
16:16 UTC Bubba and Evan to end Y for PCAL calibration. Set ISI config to SC_OFF_NOBRSXY.
16:21 UTC Karen and Christina to end stations
16:25 UTC Joe D. to LVEA (eye wash, fire ext., etc.)
16:27 UTC Carlos restarting nuc for control station camera control
16:30 UTC Gerardo to end X
16:40 Jeff B into LVEA near HAM2 for WP#
16:41 Fil into LVEA near HAM6 for WP#6389
16:44 Travis transitioned EY to LASER HAZARD
17:11 Ken done his work in the warehouse and headed to the LSB
17:16 Christina leaving EX and heading for the LVEA
17:29 Gerardo back from EX
17:40 Due to exemplary siesmic isolation efforts, work being done around HAM2 has failed to cause lockloss! So I've manually broken the lock to afford others the opportunity to work.
17:47 Cheryl into PSL anteroom to look for I/O parts.
17:55 Charndra into LVEA to check gate valves WP#6445
18:00 FIl done in LVEA and headed to EX
18:02 Karen back from EY and heading into the LVEA
18:05 Jim doing measurement on HAM1. Will involve RMs and deisolating HAM1 HEPI
18:06 Multiple corner watchdog trips occurred, maybe because of Chandra in the biergarten near the STS??
18:14 Jeff B out to Ends/complressor rooms to check dust monitor
18:15 Dave and Jim B to mechanical room.
18:20 Joe D out of the LVEA
18:21 Dick G into CER
18:23 Evan and Travis done at EY. It is SAFE
18:27 Jim and Dave back
18:30 Cintas on site to change mats
18:40 Cheryl out
18:50 Cheryl and Betsy out to Mid Stations - 3IFOI inventory
18:56 Chandra out of LVEA and headed out to EX
18:57 Joe D out to LVEA to run the oxidation out of the eyewash water
19:10 Jeff B out
19:13 Travis out
19:27 Robert to EY
19:38 Cheryl and Betsy back
19:42Karen out of LVEA and Jason and Betsy to MY
19:44 DAQ restart imminent
19:47 DAQ has been restarted....and we're back
20:33 Begin initial alignment
21:16 Begin Locking sequence
23:28 Intention Bit set to Undisturbed