Displaying report 1-1 of 1.
Reports until 16:00, Tuesday 07 February 2017
H1 General
jeffrey.bartlett@LIGO.ORG - posted 16:00, Tuesday 07 February 2017 (33979)
Ops Day Shift Summary

Ops Shift Log: 02/07/2017, Day Shift 16:00 – 00:00 (08:00 - 16:00) Time - UTC (PT)

State of H1: IFO unlocked after maintenance window. Started initial alignment    
Intent Bit: Commissioning/Locking
Support: N/A
Incoming Operator: Travis
 
Shift Summary: Down for entire shift for maintenance. After work in the PSL finished started and initial alignment. Travis will finish the initial alignment.   
 
Activity Log: Time - UTC (PT)
16:00 (08:00) Take over from TJ
16:19 (08:19) Richard – Going to End-X to work on Beckhoff Safe System
16:20 (08:20) Peter – Going into PSL to retrieve cables
16:21 (08:21) Chris – Escorting pest control in LVEA
16:24 (08:24) Lockloss – Maintenance window
16:28 (08:28) Bubba – Going to CS roof to check equipment
16:31 (08:31) Joe – In LVEA to service batteries
16:33 (08:33) Karen – Cleaning at End-Y
16:33 (08:33) Chris – Finished in LVEA
16:33 (08:33) Chris – Escorting pest control along the Y-Arm  
16:34 (08:34) Peter – Out of the PSL
16:41 (08:41) Cintas on site to service mats
16:42 (08:42) Hugh & Jim – Going to End-Y to center BRS (WP #6469)
17:00 (09:00) Bubba to escort water delivery to both end stations
17:02 (09:02) Kyle – Going into the LVEA to check equipment on elevated slabs
17:03 (09:03) Chris – Finished on Y-Arm
17:03 (09:03) Chris – Escorting pest control along X-Arm
17:10 (09:10) Richard – Back from End-Y
17:15 (09:15) Cheryl – Going into the PSL (WP #6468)
17:16 (09:16) Filiberto – Going into CER to label cables – May also go into LVEA
17:21 (09:21) Kyle – Out of the LVEA
17:25 (09:25) Betsy – Going into west bay to work on 3IFO stuff
17:28 (09:28) Chandra – Going into the LVEA to inspect vacuum equipment
17:34 (09:34) Kyle – Going into the VEAs at both end stations
17:52 (09:52) Apollo on site to see Bubba
17:53 (09:53) Jason – Going into the PSL
17:55 (09:55) Karen – Leaving End-Y
17:56 (09:56) Christina – Leaving End-X
18:01 (10:01) Richard – Going into LVEA to do some cabling
18:02 (10:02) Bubba – Back from both Ends
18:05 (10:05) Bubba – Escorting Apollo in LVEA to inspect HVAC
18:12 (10:12) Joe – Out of the LVEA
18:16 (10:16) Richard – Finished in the LVEA
18:17 (10:17) Richard – Going to End-X to install cable
18:23 (10:23) Norco – N2 delivery to CP2
18:30 (10:30) Jason – Out of the PSL Enclosure
18:37 (10:37) Cheryl – Out of the PSL
18:39 (10:39) Richard – Out of the LVEA
19:01 (11:01) Richard – Going to HAM6 to check wiring
19:12 (11:12) Richard – Out of the LVEA
19:27 (11:27) Kyle – Back from the end stations
19:28 (11:28) Kyle – Going into the LVEA for vacuum equipment checks
19:30 (11:30) Bubba & Apollo – Out of the LVEA
19:35 (11:35) Joe – Out of the LVEA
19:47 (11:47) Betsy – Out of the LVEA
21:00 (13:00) Cheryl & Sheila – In the PSL to fix a clipping problem
22:15 (14:15) Hugh & Jim – Back from End-Y – BRS is still a problem
22:30 (14:30) Cheryl out of the PSL - Kiwamu in the PSL
23:30 (15:30) Shelia & Kiwamu – Out of the PSL
23:30 (15:30) Sheila – Finished the LVEA sweep that I had started earlier
23:35 (15:35) Start initial alignment
00:00 (16:00) Turn over to Travis
Displaying report 1-1 of 1.