Reports until 09:28, Friday 10 February 2017
H1 General
jeffrey.bartlett@LIGO.ORG - posted 09:28, Friday 10 February 2017 (34041)
Ops Day Shift Transition
Ops Shift Transition: 02/10/2017, Day Shift 16:00 – 00:00 (08:00 - 16:00) - UTC (PT)
 
State of H1: IFO relocking after large earthquake in the Philippines  
Intent Bit: Commissioning/Locking
Weather: Wind is Light to Moderate Breeze (6 - 15 mph), Upper 30s and clear
Primary 0.03 – 0.1Hz: Currently between 0.07 and falling  
Secondary 0.1 – 0.3Hz: Currently at 0.6um/s and trending slightly upwards
Quick Summary: Relocking after EQ      
Outgoing Operator: Jim
 
   This post is late due to (1) reclocking issues with OMC and (2) adding new PI modes to the monitoring systems. As of 17:23 (09:23) LHO is back into Observing.