EY Gate Valve closed (John, Kyle)
-
Installation of EY Oplev Housings (Thomas, Mark D.)
-
Lots of One-Arm work (which was being coordinated with SEI/SUS measurements & the oplev work)
-
EX Weather Station re-started (Patrick)
-
H1 iLIGO EY Oplev beam enclosure removed from viewports (Gerardo)
As of around 4pm, sounds like the Gate Valve (GV18) will be opened tonight for OAT work.