H1 SEI
hugh.radkins@LIGO.ORG - posted 17:02, Thursday 12 July 2012 (3424)
H1 HAM3 HEPI Work
Greg Jim & Hugh
We tweaked the position again per IAS (Jason) and then set to attaching HEPI Actuators.  We ended up behind where we started when we found we were unable to attach the Actuator on the NW corner.  We had to jack up the Crossbeam and slide the HEPI Housing East.  This gets quite involved and we are now out of position again based on the Dial Indicators.  We'll continue with attachment and may request looks by IAS as we go.