TITLE: 02/24 Day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Commissioning
INCOMING OPERATOR: Cheryl
SHIFT SUMMARY: We have been in a commissioning mode since 17:27 UTC. Since then we have had to wait out a 6.9M EQ from Fiji, and many people took advantage of the down time to get work done. We are locked again and do more coherence tests while waiting for the OK from LLO.
LOG:
- 17:21 Chandra to EY to check on ion pump cable short
- 17:22 Hugh, Vaishali to EY to center T240
- 17:25 Transitioned the SEI configuration from WINDY to VERY_WINDY_NOBRSXY since people will be visiting the end stations.
- 17:27 Intention bit set to Commissioning
- 17:50 Lock loss. 6.9 EQ in Fiji
- 17:52 Changed SEI config to LARGE_EQ_NOBRSXY retroactively. This was in hope to keep platforms from tripping after they were reisolated.
- 17:56 Dave B to Mids and ends to take pictures and inventory.
- 17:57 Chandra back.
- 18:34 Marc, Chandra to EY to test iop pump
- 18:54 Dave back
- 18:59 Richard to EY to join Marc and Chandra
- 19:00 Charge measurements started
- 19:37 Richard, Marc, Chandra back
- 19:59 Charge done
- 20:00 Searched for home on the PSL rotation stage since we haven't quite been at 30W lately.
- 20:08 SEI_CONF back to WINDY
- 21:33 Keita, Heather reloaded filter coefficient for OAF