Reports until 16:05, Saturday 04 March 2017
H1 General
jeffrey.bartlett@LIGO.ORG - posted 16:05, Saturday 04 March 2017 (34578)
Ops Day Shift Summary
Ops Shift Log: 03/04/2017, Day Shift 16:00 – 00:00 (08:00 - 16:00) Time - UTC (PT)
State of H1: Locked at NLN, range is 65.9 Mpc  
Intent Bit: Observing for 18 hours.
Support: N/A
Incoming Operator: Jim

Shift Summary: Diag Reset for Timing error on H1IOPASCO. Ran A2L script – Pitch is slightly elevated and Yaw remains below the reference. Good shift for observing. No problems or issues to report.      

Activity Log: Time - UTC (PT)
16:00 (08:00) Take over from Cheryl
16:17 (08:17) Diag Reset of H1IOPASCO Timing error
16:30 (08:30) Ran A2L check script
00:00 (16:00) Turn over to Jim