Reports until 09:41, Wednesday 08 March 2017
LHO General
vernon.sandberg@LIGO.ORG - posted 09:41, Wednesday 08 March 2017 (34679)
Work Permit Summary for 2017 March 07
Work Permit Date Description alog/status
6517.html 3/7/17 13:45 Bail tumbleweeds to allow access to Mid and End Stations on both arms. This will continue through today and tomorrow. 34664
6516.html 3/7/17 13:37 Swap out existing controllers with modified controllers on VARIC transformers used to control temperatures in LVEA, Mid and End Stations.  
6515.html 3/6/17 15:40 Mark and drill (9) ea. holes in LVEA floor, (4) ea. beneath CP1, (4) ea. beneath CP2 and (1) each near NW corner of BSC8 beneath iLIGO RGA. Requires the use of a hammer drill. Dust will be minimized by use of water, wet towels and portable HEPI filtered vacuum cleaner. FRS Ticket 7456,
E1700073-v1,
Alog 34652
6514.html 3/6/17 12:19 Install new h1hfwsca0 Switch was configured (sw-msr-h1au) port 22 34645
6513.html 3/6/17 9:54 Replace the laser in the ITMy optical lever with one that has been thermally stabilized. This requires installation of the thermal stabilization cooler and armored fiber. I will have to briefly remove the cover of the oplev transmitter pylon for the fiber swap; the enclosure front panel, bellows and viewport cover will not be removed. The ITMy oplev has been involved in several hveto round wins, this work is an attempt to curb this issue. 34646
6512.html 3/6/17 9:48 Increase power on ETMx and ETMy oplevs to attempt to decrease glitching. ETMx/y oplevs have been responsible for several hveto round wins due to glitching, this is an attempt to lessen that while I work on stabilizing replacement lasers for these oplevs. No viewports will be exposed during this work.  
6511.html 3/6/17 8:32 Replace HWS BS beam dumps. Install GigE camera and pickoff mirror on HWSX. 34643, 34649
6510.html 3/2/17 5:33 Inspect the PSL Chiller coolant lines with high intensity light looking for trapped air. Inspection will focus on the highest sections of the pipe runs, all downward turning elbows, and tees.  34658
6509.html 3/1/17 19:13 SVN maintenance: “/ligo/www/www” working directory should be reverted from svn1.8 back to svn1.6.  
       
Previous W.P.s      
6361.html 11/29/16 8:59 Reconfigure power to the Vault equipment to provide +-12Vdc instead of just +12. Power up equipment and get signals to MidX 34659