Reports until 16:06, Thursday 16 March 2017
LHO General
patrick.thomas@LIGO.ORG - posted 16:06, Thursday 16 March 2017 (34874)
Ops Day Shift Summary
TITLE: 03/16 Day Shift: 16:00-00:00 UTC (08:00-16:00 PST), all times posted in UTC
STATE of H1: Observing at 68Mpc
INCOMING OPERATOR: Corey
SHIFT SUMMARY: Remained locked entire shift. TCS ITMY CO2 guardian took us out of observing multiple times at the beginning of the shift (accepted SDF differences attached). Bubba ran the fire pumps and I ran a2l when LLO lost lock.
LOG:

16:04 - 16:31 UTC: TCS ITMY CO2 guardian periodically taking us out of observing.
16:37 UTC LLO down. Bubba running fire pumps. Out of observing.
16:41 UTC running a2l.
16:46 UTC Bubba done running fire pumps. a2l done.
16:47 UTC Back to observing.
17:03 UTC GRB. LLO down.
18:02 UTC Betsy and Vern to both mid stations.
18:12 UTC Karen to optics lab
18:48 UTC Karen out of optics lab
19:33 UTC Cheryl to optics lab
19:47 UTC Elisabeth has car parked by H2 enclosure to move cables from enclosure to car and then mid Y.
20:00 UTC Elisabeth to mid Y
20:19 UTC Bubba to mid X to drop off wire
20:27 UTC Jeff B. driving to receiving, opening outside rollup door, putting ladder inside.
20:29 UTC Chandra to mid Y to check on thermocouples in discharge lines
20:35 UTC Jeff B. done
20:36 UTC Elisabeth back from mid Y
20:45 UTC Chandra back
21:29 UTC Gave Carlos remote access to check whatsup
21:52 UTC Betsy and Hugh to mid X
22:09 UTC Marc and Elisabeth to mid Y
22:24 UTC Cheryl done in optics lab
22:33 UTC Marc and Elisabeth back
Images attached to this report