jim.warner@LIGO.ORG - posted 14:27, Thursday 19 July 2012 (3507)
LHO BSC assembly starting back up
A few days ago the first 2 plates for LHO's next BSC were brought to the staging building. The first of these (D0900894-v2, s/n 1) was placed on the granite table today, and will be helicoiled over the next couple weeks, in between work on other install tasks. We won't really be able to get back into production of BSC's until at least one of the test stands can be switched back to a BSC configuration, but that is hopefully no more than a week or two out.