jeffrey.bartlett@LIGO.ORG - posted 14:13, Thursday 13 April 2017 (35528)
Dropping Intent Bit to Commissioning
   Dropping the intent bit to commissioning so Robert can work on the list below. I just spoke with LLO and they are still working their issues. Will keep in contact with LLO Ops on status. 

Commissioning Activities:

1). Shake input arm below 8 Hz
2). Bang on HAM6 to make sure dust doesn’t produce blip glitches
3). Look into mitigating scattering on ISCT1 so we can use POP AIR