Yesterday we:
- Replaced the HWS enclosure panel with wider apertures and attached the beam tubes to the flanges
- Removed the lexan covers from the viewports and covered the slots with the mating semi-circular pieces
- Aligned the HWS SLED beam to the center of the upper periscope mirrors.
- Using an IR viewer and counting turns on the upper periscope mirrors, we aligned the HWS SLED beams to the center of the in-vacuum lenses visible just inside the viewports
- Replaced the OLD HWS SLED (QSDM-840-5)
- Old SLED: #07.14.265 (Max current: 153mA)
- New SLED: #07.14.266 (Max current allowed: 195mA)
- We retained the hardware current limit at 110mA.